Amarillo ISD Committee Weighs School Closures and Rebuilds; Trustees to Hear Plan in December

A community advisory committee for Amarillo ISD reviewed three possible plans Tuesday for dealing with falling enrollment, ranging from closing a handful of campuses with no construction to a 15-year rebuilding effort, according to the Amarillo Tribune. The committee is expected to choose a direction by Nov. 17 and bring guidance to the school board in December.

More than 40 people attended the Nov. 3 meeting at the AmTech Banquet Hall. The group has been meeting since September. Bob Templeton, a senior consultant with STRIVE Public Policy Resources, presented the options, which he said grew out of the committee’s earlier discussions. Templeton said members have stressed protecting district programs, keeping approaches consistent, accounting for feeder patterns into all high schools, communicating clearly with the community and avoiding a rushed decision.

Elementary campuses are using about 70% of their available seats, and that could drop to 61% in five years if enrollment keeps falling, the Tribune reported. The district shut three elementary schools at the start of last school year, and then-Superintendent Doug Loomis said in March 2025 that more consolidations were possible. Templeton noted that 35 of the district’s 50 campuses date to before 1960, built for post-World War II population growth, and said the options account for the age of those buildings.

Amarillo ISD announced the committee’s formation Oct. 7. It said the group’s task is a plan to raise building utilization districtwide to 80% by the 2029-30 school year. Current utilization is 74.5%, according to the district. Enrollment is projected to fall by about 3,000 students over the next five years, which would push utilization to near 63% without changes.

Path A is the least costly and requires no construction, Templeton said, and it could take effect for the 2027-28 school year. Three elementary campuses would close: Carver Early Childhood Academy, whose students would join George Washington Carver Elementary Academy; Landergin, with students moving to Lamar; and Wills, with students moving to San Jacinto. The Allen, Travis and Bowie sixth-grade campuses would also close, and those students would attend sixth grade at their middle schools. Attendance boundaries would change for Bonham and Crockett middle schools and for Austin and Houston middle schools. Templeton projected utilization of 74%.

Path B would turn the Travis and Bowie sixth-grade campuses into elementary schools built for 750 students each. Templeton said they were picked as among the district’s newest buildings. Travis had 250 students last school year and Bowie had 346. Oak Dale, Western Plateau, Coronado and Avondale elementary schools would expand, and 10 smaller campuses, among them Wolflin, Landergin, Sanborn and Glenwood, would close, with boundaries redrawn. Templeton estimated the plan would take almost three years, would need funding for renovations and would reach 76% utilization.

Path C would replace buildings constructed before 1965, covering 12 to 14 elementary schools and four middle schools, in four phases beginning with the oldest structures. The plan does not name affected schools. The first phase of new schools would open in 2030 and the second in 2034, with the final two phases finishing in 2038 and 2041. Templeton said the plan would take about 15 years and four bond elections, and utilization would be near or above 80% after each phase while enrollment projections continue to decline.

All three plans would close or renovate the Allen, Travis and Bowie sixth-grade campuses. Paths A and B would both close Landergin and possibly Wills elementary schools.

The committee meets again Nov. 17 to give more feedback before a plan goes to trustees in December. Meeting slides and recordings are posted on the district’s website.