Harlingen WaterWorks Manager Says Utility Can Meet Data Center Reclaimed Water Contract

Harlingen WaterWorks General Manager Marie Leal says the utility’s production records indicate it can handle a contract to deliver reclaimed water, with a ceiling of 4.6 million gallons daily, to the developer of a proposed data center, per the Valley Morning Star.

Eneus Energy has proposed a data center campus covering 1,780 acres outside the city limits, and the contract is tied to it. In September 2025, the WaterWorks board, acting on a recommendation from interim General Manager Roy Rodriguez, voted unanimously to sign an agreement with RGV Property Group. The company would be entitled to as many as 4.6 million gallons daily at 75 cents per 1,000 gallons, and the contract calls for a $1.2 million yearly payment if its daily average tops roughly 4.6 million gallons across a year.

The delivery schedule assumes the data center begins operating this year. It calls for 0.5 million gallons a day in the last three months of 2026, with potable water standing by as a backup, then 1.3 million by late 2027, 2.7 million by late 2028, 4.1 million by late 2029 and 4.6 million by late 2030.

The contract lists WaterWorks’ reclaimed output at roughly 5 million gallons daily. Leal, who has led the utility since late September, said its reports put the average nearer 5.5 million and growing with the city’s population. “Our effluent has gone up substantially — 5 to 6 million gallons a day,” Leal said.

Leal said the plant records she reviewed, covering 2020 through 2026, show output topping 4.6 million gallons most of the time. She cited a few dips: the winter of 2020-21, when it fell to 4.4 million; December 2021, at 4.40 million; and February 2023, at 4.36 million. In both 2024-25 and 2025-26, she said, output stayed above 4.6 million and averaged about 5.5 million.

Resident Erin Dahl reached a different conclusion for 2023. In an emailed message, she said her review found recorded flow “was below 4.6 million gallons per day on 152 of 365 days.” The newspaper’s own review of the utility’s charts from 2018 to May 2025 showed Aug. 4, 2024 was the last day production dipped under 4.6 million gallons.

The contract obliges WaterWorks to cover any reclaimed shortfall with drinking-quality water. During negotiations in July 2025, Eneus Energy’s John Metz, a senior vice president of engineering and project development, emailed then-assistant General Manager David Sanchez to ask what WaterWorks could provide to confirm the backup water would be available. Sanchez replied that “potable currently is not an issue. It is the reclaimed that we have limited supply of.” After reading the exchange, Leal said WaterWorks has a restricted reclaimed supply but plentiful potable supply.

The agreement runs two decades from the start of commercial operations and renews on its own for two 15-year terms, for as many as 50 years in all. Residents have pressed commissioners for months to order a legal review, arguing the deal could commit the city’s drinking water as well as reclaimed water for that length of time.

WaterWorks’ reclaimed water must satisfy the conditions of its state wastewater discharge permit. The buyer may refuse water that misses those standards, and WaterWorks would then have to cover the volume with drinking-quality water until levels return to range. The contract also lets WaterWorks’ delivery duty be curtailed by circumstances including fire, flooding, hurricanes, drought, shortages of materials and acts of God.